Minor Works to be done on High Voltage (HV) ring and Substations.

From Saturday 2 December, works on the HV ring main and Substations throughout Murdoch University’s Perth Campus will commence.

Please see following dates and areas that will be affected.

  • 2 December: Substations MSR1, 2, 16, 20, and 21 this will affect All farm areas including Residence, Central stores area and surrounding Buildings, ETC and surrounding buildings and Algal Research we will have Generators in place to hold up critical equipment.
  • 3 December: Substations MSR2 and 1 this will affect Wesfarmers and Fire Ring Main Pump station.
  • 4 December: Substation 14 this will affect building 120 thru to 129 Murdoch College.
  • 7 December: Substations 9, 23 and 25 this will affect Building 525 and Student Village.
  • 8 December: Substation 8 this will affect Grounds area and Student village Stage 5 & 6.
  • 9 December: Substation 5 this will affect buildings 354, 357, 460, 461, 462 and 465.
  • 10 December: Substation 7 this will affect buildings 246,490,491 and 492.
  • 11 December: Substation 11 this will affect buildings 410, 411, 412, 415, 418 and Building site.
  • 14 December: Substation 6 this will affect buildings 380, 381, 382, 383, 384, 385, 386, 387, and 388.
  • 15 December: Substation 24 this will affect buildings Chiller Plant room 3.
  • 16 December: Substation 4 this will affect buildings 249, 301, 335, 340, 341, 342, 344, 350, 351, 352, 353, and 355.
  • 17 December: Substation 10 this will affect buildings 435, 436, 440, 448, 450, 451, 452, 453, 510, 512, 513 and 515.
  • 19 December: Substation 3 this will affect buildings 130 to 142, 170, 172, 250, 251, 252, 255, 260, 261, 262, 263, 265, 270, 175 and 180.
  • 21 December: Substations 18, 26 and 27 this will affect buildings 706, 730, 731, 732, 733, 734, 735, 736, 739, 740, 742, 743, 744, 745 and 747.
  • 27 December: Substation 12 this will affect buildings 305 and 330.
  • 28 December: Substation 13 this will affect buildings 220, 223, 224, 226, 227, 228, 229, 230, 235, 244, 245 and 247.

 